OTHERS VSOLAR GROUP BERHAD (VSOLAR OR THE COMPANY)
EXTENSION OF TIME FOR THE UTILISATION OF PROCEEDS RAISED FROM RENOUNCEABLE RIGHTS ISSUE OF 1,232,492,289 NEW VSOLAR SHARES TOGETHER WITH 821,661,526 FREE DETACHABLE WARRANTS IN VSOLAR (RIGHTS ISSUE WITH WARRANTS 2020)
VSOLAR GROUP BERHAD
Type
Announcement
Subject
OTHERS
Description
VSOLAR GROUP BERHAD (VSOLAR OR THE COMPANY)
EXTENSION OF TIME FOR THE UTILISATION OF PROCEEDS RAISED FROM RENOUNCEABLE RIGHTS ISSUE OF 1,232,492,289 NEW VSOLAR SHARES TOGETHER WITH 821,661,526 FREE DETACHABLE WARRANTS IN VSOLAR (RIGHTS ISSUE WITH WARRANTS 2020)
(For consistency, the abbreviations used throughout this announcement shall have the same meanings as defined in the announcements dated 6 December 2019, 1 June 2023, 12 July 2024, 10 March 2025,14 August 2025 and 4 March 2026 in relation to the Rights Issue with Warrants 2020, where applicable, unless stated otherwise or defined herein.)
The Board of Directors of Vsolar (Board) wishes to inform that as of 9 July 2026, the Company has yet to fully utilise the proceeds raised from the Rights Issue with Warrants 2020 and the Board requires additional time to utilise the balance proceeds amounting to RM25.548 million for the capital expenditure for development and construction of biomass/biogas plants (Extension of Time).
The Board has resolved to extend the time frame for the utilisation of the said proceeds for another twelve (12) months period from 13 July 2026 to 12 July 2027 (Revised Time Frame) to provide additional time for the Group to utilise the balance of proceeds for the purpose.
The details of the Revised Time Frame are as follows:
Purpose
Proposed Utilisation
RM'000
Actual Utilisation
RM'000
Unutilised Proceeds
RM'000
Utilisation timeframe from the Receipt of Proceeds from the Date of Listing, i.e. 13 July 2020
Intended Time Frame for Utilisation
Proposed Revised Time Frame
Capital expenditure for development and construction of biomass/biogas plants
25,548
-
25,548
Within 72 months
12 July 2026
12 July 2027
Working capital
2,040
-
2,040
Within 60 months from the completion of the construction of biomass/biogas plants
-
-
Development of 30.05MWp Large Scale Solar Photovoltaic (PV) Energy Generating Facility
8,537
(7,819)
718
Within 24 months from the variation
9 March 2027
-
Estimated expenses for the Rights Issue with Warrants
850
(850)
-
Within 1 month
-
-
Total
36,975
(8,669)
28,306
-
-
-
The Revised Time Frame does not require the approval of any regulatory authorities or the shareholders of Vsolar.
The Board, having considered all aspects of the proposed Extension of Time, is of the opinion that it will not have material adverse effect on the financial performance of the Group and is in the best interest of the Group.
The Company shall continue to be vigilant and prudent in managing the remaining proceeds raised from the Rights Issue with Warrants 2020 and will continue to disclose the status of the utilisation in the Company's quarterly results and annual reports until it is fully utilised.