MATERIAL LITIGATION Citaglobal Berhad (formerly known as WZ Satu Berhad) ("the Company" or "CITAGLOBAL") - Update on Adjudication under the Construction Industry Payment & Adjudication Act 2012 by Proweld Engineering Sdn. Bhd. against Citaglobal Energy Sdn. Bhd. (formerly known as WZS Misi Setia Sdn. Bhd.)
| CITAGLOBAL BERHAD |
| Type | Announcement |
| Subject | MATERIAL LITIGATION |
| Description | Citaglobal Berhad (formerly known as WZ Satu Berhad) ("the Company" or "CITAGLOBAL") - Update on Adjudication under the Construction Industry Payment & Adjudication Act 2012 by Proweld Engineering Sdn. Bhd. against Citaglobal Energy Sdn. Bhd. (formerly known as WZS Misi Setia Sdn. Bhd.) |
|
Further to the Company’s announcement made on 27 July 2022, the Board of Directors of the Company wishes to announce that Citaglobal Energy Sdn. Bhd. (formerly known as WZS Misi Setia Sdn. Bhd.) (“Citaglobal Energy”), a wholly-owned subsidiary of the Company was on 5 December 2022 notified by its appointed solicitors that the Adjudicator had on 5 December 2022 determined and delivered the Adjudication Decisions pursuant to a claim by Proweld Engineering Sdn. Bhd. (“PESB”) against Citaglobal Energy arising from work orders for the piping and mechanical works for the ASPAC KANCIL Project awarded by Citaglobal Energy to PESB on 16 October 2020 (“ASPAC KANCIL Project”). Background on the ASPAC KANCIL Project Citaglobal Energy, had received a purchase order amounting to approximately RM16.5 million dated 9 October 2020 from AsPac Lubricants (Malaysia) Sdn. Bhd. (“AsPac Lubricants”), a member of the BP Group of Companies, with its office address at Lot No. 197 II & 197 III, Jalan Pelabuhan Utara, 42000 Pelabuhan Klang, Selangor Darul Ehsan for the mechanical, electrical and instrumentation installation works for its lubricant blending plant (“the Contract”). Citaglobal Energy’s scope of work are mechanical, electrical and instrumentation installation works in line with the plant upgrading for AsPac Lubricants in Port Klang, Selangor Darul Ehsan including supply of partial materials, construction and commissioning of the upgrading system. The Adjudication Decisions are as follows:
Citaglobal Energy is seeking the advice of its solicitors with regards to its recourse against PESB for back charges payable by PESB to Citaglobal Energy as well as its recourse to review or appeal the Adjudication Decisions. Citaglobal Energy intends to claim back charges against PESB following PESB’s discontinuance of its obligations under the Contract without Citaglobal Energy’s consent. The Adjudication Decisions will not have any material financial effect to Citaglobal group of companies. This announcement is dated 6 December 2022. |
|
Announcement Info
| Company Name | CITAGLOBAL BERHAD |
| Stock Name | CITAGLB |
| Date Announced | 06 Dec 2022 |
| Category | General Announcement for PLC |
| Reference Number | GA1-06122022-00035 |